News: KLAX runway closures

Posted Thursday, March 12, 2015

KLAX has started a long term runway construction project. During this project (which will go until mid 2017) each of the four runways will be closed, one at a time. PilotEdge will be simulating these closures.

The runways are scheduled to close per the following schedule:

Runway 25L/7R – March 2015 to April 2015
Runway 24R/6L – June 2015 through October 2015
Runway 24L/6R – November 2015 through October 2016
Runway 25R/7L – October 2016 through June 2017

During each closure the adjacent runway will take over the duties of the closed runway. As a result, runway 25R will be both an arriving and departing runway when 25L is closed.